LASG Rolls Out 3-Week Traffic Diversion Plan For Oke-Afa , Isolo Bridge Rehabilitation

Share
Share

The Lagos State Government has rolled out a traffic management plan ahead of the commencement of rehabilitation works on Oke-Afa Bridge in Isolo Local Government Area. The rehabilitation is scheduled to commence on Friday, 28th August, 2026, and run for three weeks, through Friday, 18th September, 2026.

Oluwaseun Osiyemi, Commissioner for Transportation LASG in a statement on Tuesday said the works will be carried out in two phases; the first phase will cover the outbound Isolo-to-Ejigbo axis of the bridge, from Friday, 28th August, 2026, to Friday, 11th September, 2026, while the second phase will cover the bridge inbound Isolo from Ejigbo, running from Saturday, 12th September, 2026, to Friday, 18th September, 2026.

ALSO READ  CBD Warns NURTW, CDAs Within Lagos Island Business District On Traffic Laws

Consequently, he noted that Oke-Afa Bridge will be temporarily closed to vehicular movement, and motorists are advised to use the following alternatives:

- Advertisement -

- Advertisement -

According to him, during Phase One rehabilitation, motorists from Isolo heading toward Ejigbo will be diverted onto the Isolo-bound carriageway from Pako Roundabout, where traffic will move in both directions, before rejoining the main carriageway to continue their journeys at Mobil Filling Station.

He explained that motorists coming from Ejigbo will maintain free movement and share the carriageway with Ejigbo-bound traffic from Mobil Filling Station to Pako Roundabout, after which they will regain full access to the road to reach their destinations.

ALSO READ  NEW YEAR: Sanwo Olu Urges Nigerians To Enter 2021 With Rekindled Hope

During Phase Two, the commissioner stressed that rehabilitation, motorists from Ejigbo heading toward Isolo will be diverted onto the Ejigbo-bound carriageway from Mobil Filling Station, where traffic will move in both directions, before rejoining the main carriageway to continue their journeys at Pako Roundabout.

*Motorists coming from Isolo will maintain free movement and share the carriageway with Isolo-bound traffic from Pako Roundabout to Mobil Filling Station, after which they will regain full access to the road to reach their destinations”,he added .

The Lagos State Traffic Management Authority, he pointed out will be on ground to coordinate vehicular movement and minimise inconveniences. In the same vein, an emergency tow vehicle will be stationed within the axis to provide quick recovery operations for breakdowns throughout the period of the works.

ALSO READ  RED RAIL LINE: Sanwo-Olu Orders Contractor To Deliver Project December

“Advisory: Motorists are implored to be patient, as the partial road closure forms part of the traffic management plan for the rehabilitation works on Oke-Afa Bridge, Isolo LGA, being carried out by the Federal Ministry of Works (Office of the Federal Controller, Lagos) through Messrs. Strabic Construction Limited.” He affirmed.

 

Share
Related Articles
Transport

Hope Uzodimma To Grace CILT Nigeria 2026 National Conference As Special Guest In Abuja

By Roland Ekama    The Executive Governor of Imo State, Senator Hope...

Transport

Logistics Professionals Must Master End-to-End Supply Chain Skills, Says SCJ Transport Boss.

Logistics and supply chain management (LSCM) professionals in Nigeria must move beyond...

Transport

LASTMA Launches 3-Day Global Best-Practices Training For Frontline Officers

The Lagos State Traffic Management Authority (LASTMA) has kicked off a three-day...

Transport

LASPA Begins Enforcement Of 2026 Parking Permit

  The Lagos State Parking Authority (LASPA) has officially commenced enforcement of...