Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

The news is by your side.

- Advertisement -

SANGOTEDO HOUSING PROJECT: Sanwo Olu Threatens To Terminate Erring  Contractors In Seven Days

Contractors engaged by Lagos State Government to handle the construction of 1,188-unit LagosHOMS in Sangotedo area of Eti Osa now have a final completion date to deliver the project.

 

 

 

After defaulting previous deadlines, Governor Babajide Sanwo-Olu mandated the contractors to finish up the 744 flats being developed in Scheme 1 of the housing project by the end of next month (October).

 

The Governor issued a stern warning to those culpable in defaulting the deadlines, saying he would no longer tolerate tardiness in the work.

 

 

- Advertisement -

- Advertisement -

Erring contractors, the Governor threatened, would have their deals terminated should there be no progress in the next seven days.

 

 

The Governor, on Friday, handed down the new deadline when he inspected the housing project to assess the pace of construction work.

 

The project, sited on 16.9 hectares, took off in 2012. It was revived by the Sanwo-Olu administration. The first scheme of the project has 62 blocks of 12 flats each, while the second scheme has 32 blocks of 444 flats.

ALSO READ  PUBLIC ALERT: NAFDAC Raises  Alarm Over Unwholesome Whippy Real Mayonaisse

 

Sanwo-Olu, who was accompanied on the inspection by members of the State’s cabinet had a one-on-one engagement with the contractors during which he expressed his displeasure over the slow work on the project.

 

 

He said: “We have come on an inspection of this massive construction site that is divided into two phases. The level of work on Phase One is over 90 percent, but this is not the same in the second phase. In the next six weeks, we will be handing over the 744 units in Phase 1 of the project and all contractors working on it must complete their work.

 

- Advertisement -

“I commend all contractors that have worked tirelessly to push through; I understand this has been a very difficult project. We have been working night and day, trying to deliver the project. We want to be fair to every contractor and we appreciate those who have shown real resilience and commitment.

ALSO READ  LOCAL CONTENT: Plateau Govt Tasks Contractors To Engage Indigenous Workers On State Projects

 

“I use this opportunity to give a stern warning to erring contractors slowing down the project. It doesn’t matter who you know, I am not going to tolerate this tardiness any longer. I will give you one week to scale up work on the project. If there is no appreciable improvement, not only are we going to terminate those erring contracts, we will also prosecute them.”

 

The Governor pointed out that there was no reason for the contractors to delay the project and postpone deadlines, stressing that the State Government had fulfilled financial obligations in the contract.

 

Sanwo-Olu directed officials of the Ministry of Housing and Ministry of Works and Infrastructure to monitor the contractors and submit progress reports on the project. He said the report would determine whether the contractors would be considered again by the State Government for other projects.

ALSO READ  Don't Involve Me In Selection Of Traditional Rulers, Gov. Oyebanji Tells Ekiti Kingmakers

 

Sanwo-Olu, at the meeting, called out the defaulters, and said: “I have not come here to turn you away, but to make peace and restitution. For those contractors still working, we will wait for another four more weeks for extensive clean-up before we finally commission the project.”

 

The Governor also set a nine-month deadline for the completion of the project’s Scheme Two, urging those handling the work to finish up before June, 2022.

 

Caption:

 

 

LagosHOMS Sangotedo Housing project in Eti Osa inspected by Governor Babajide Sanwo-Olu, on Friday, September 17, 2021. INSET L-R:  Permanent Secretary, Ministry of Housing, Mr. Wasiu Akewusola; Commissioner for the Environment & Water Resources, Mr. Tunji Bello; Special Adviser to the Governor on Housing, Mrs. Toke Benson-Awoyinka; Governor Babajide Sanwo-Olu and Commissioner for Housing, Mr. Moruf Fatai-Akinderu during the inspection.

 

 