Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

The news is by your side.

- Advertisement -

LASG Announces Closure Of Abule-Apapa Railway Level Crossing Project

The Lagos State Ministry of Transportation has announced plans to temporarily close Abule Level Crossing towards Apapa end of the railway project for construction on the rail track in continuation of the ongoing Nigeria Railway Modernisation Project (Lagos-Ibadan section).

A statement issued on Friday by the State Ministry for Transportation, said that the Abule Level Crossing will be closed from Saturday, 21st of November, to Sunday, 22nd of November, 2020, for the scheduled construction.

It stated further that the Construction Company, China Civil Engineering Construction Company (CCECC) Nigeria Limited, would commence the track construction at 5:00am on Saturday and finish by 8:00pm on Sunday.

- Advertisement -

- Advertisement -

As a result of the planned closure on the aforementioned route for construction works, the release informed that the new Costain Bridge will be opened to all motorists on the 19th of November to serve as an alternative route for motorists plying the axis to aid their movement.

ALSO READ  LASG Threatens To Disallow Rickety Vehicles From  Accessing Seaports

It advised motorists coming from Oyingbo to access Funsho Williams Avenue, Iponri, Surulere for connecting the newly constructed Costain Bridge through Apapa Road to their destinations. While motorists from Eko Bridge heading towards Iponri, Funsho Williams Avenue will also utilise the newly constructed Costain Bridge through Costain Round About to reach their destinations.

Road users that are Apapa, Iganmu and Lagos Island-bound from Funsho Williams Avenue, Surulere, Iponri can make use of the newly constructed bridge to Costain Round About. Motorists coming from Franklin Street, Park Road and Abule-Nla Road and intend to connect Iponri/Funsho Williams Avenue would be diverted to Apapa Road through Ademuyiwa and Ijero Streets to connect Costain Roundabout to link the newly constructed bridge.

Advising motorists to comply with the traffic directions put in place to minimise inconveniences during the period, the Lagos State Government reiterated its determination to provide a seamless multi-modal transport system that will meet the transportation needs of its large population.

ALSO READ  LASTMA Releases Traffic Update For Apapa, Mile 2, Isolo, Others As At 9Am 

 

- Advertisement -

Meanwhile, the Lagos State Debt Management Office (DMO) Friday, inspected the ongoing Blue Line Light Rail project, which is being partly funded with N87.5 Billion Bond series, to ascertain the level of progress in preparation for the Securities and Exchange Commission (SEC) visit and also to ensure that the funds were properly expended.

The Leader of the Inspection team and Permanent Secretary, Debt Management Office (DMO), Mr. Olujimi Ige, expressed satisfaction with the status of work done on the rail project, noting that the project was abandoned sometime in 2016 with the hope that the project will be restarted and ready for use soon.

He said the Light Rail project, expected to run from Badagry to Marina, will have several platforms for passengers to buy tickets, embark and disembark from the platform.

ALSO READ  CBD Warns NURTW, CDAs Within Lagos Island Business District On Traffic Laws

According to the Engineers handling the project, the Mile-2 to the National Theatre section, which is Phase II and III is 98% completed, while Phase IV is from the National Theatre to Marina.

He explained that some areas of the project platform are elevated (Iganmu to Marina), while some are on ground in the middle of the Lagos-Badagry Expressway.

The Engineers also stated that four stations have been completed, as well as other elements which include the tracks works, while work is still ongoing on the phase IV bridge works.

The Blue Rail project is expected to improve connectivity between Badagry and Lagos in a more efficient way and less travel time.

 

 

 